Apex Mobility Systems Ltd. manufactures smart airport luggage carts used in major international airports. The company operates a centralized factory…

CA Intermediate · 4 - Cost and Management Accounting · RTP · September 2026
Apex Mobility Systems Ltd. manufactures smart airport luggage carts used in major international airports. The company operates a centralized factory with two production departments—Fabrication and Assembly, and two service departments—Stores and Maintenance. Due to rising operational costs and increased competition, management has decided to analyze overhead allocation and costing accuracy for better pricing and profitability decisions. For the financial year ending 31st March 2026, the following budgeted data is available: Department Amount (₹) Fabrication 18,20,000 Assembly 9,60,000 Stores 3,00,000 Maintenance 2,40,000 Other Overheads (₹) Particulars Amount (₹) Factory Rent 18,00,000 Building Insurance 2,00,000 Plant Insurance 2,40,000 Depreciation on Machinery 3,20,000 Canteen Subsidy 5,00,000 Direct Costs (₹) Department Material (₹) Labour (₹) Total (₹) Fabrication 75,00,000 10,00,000 85,00,000 Assembly 2,00,000 15,00,000 17,00,000 Additional Information Basis Fabrication Assembly Stores Maintenance Floor area (sq. m.) 30,000 12,000 3,000 5,000 Plant value (₹) 20,00,000 10,00,000 1,00,000 2,00,000 Store requisitions 4,000 2,000 — — Maintenance hours 3,000 2,500 500 — No. of employees 150 100 40 20 Machine hours 35,00,000 80,000 — — Labour hours 80,000 30,00,000 — — The company also received a special job order (Job No. AMS-101) with the following details: Direct Material = 1,50,000 Direct Labour: Fabrication: 300 hours @ ₹20/hr Assembly: 200 hours @ ₹20/hr Machine hours: Fabrication: 250 hours Assembly: 180 hours You are required to answer the following questions: Part 1: Total overhead allocated from Stores Department to production Department is: (A) (A) ₹2,53,099 (B) (B) ₹5,43,669 (C) (C) ₹5,06,197 (D) (D) ₹5,01,486 Part 2: Total overhead allocated from Maintenance Department to other Department is: (A) (A) ₹5,43,669 (B) (B) ₹5,01,486 (C) (C) ₹5,06,197 (D) (D) ₹42,186 Part 3: Most appropriate overhead recovery rate for Fabrication Department is: (A) (A) ₹1.21 per machine hour (B) (B) ₹12 per machine hour (C) (C) ₹20 per machine hour (D) (D) ₹4.56 per machine hour Part 4: Most appropriate overhead recovery rate for Assembly Department is: (A) (A) ₹18 per labour hour (B) (B) ₹2.50 per labour hour (C) (C) ₹20 per labour hour (D) (D) ₹0.71 per labour hour Part 5: Full production cost of Job No. AMS-101 is: (A) (A) ₹2,20,000 (B) (B) ₹2,50,099 (C) (C) ₹1,60,445 (D) (D) ₹3,62,525

Suggested Answer and Working Notes:

Part 1: Correct answer: (B) ₹5,43,669. Part 2: Correct answer: (C) ₹5,06,197. Part 3: Correct answer: (A) ₹1.21 per machine hour. Part 4: Correct answer: (D) ₹0.71 per labour hour. Part 5: Correct answer: (C) ₹1,60,445.

Topics: Overheads - Absorption Costing Method, Job Costing

ICAI Exam Preparation & Marks Distribution Resources

Explore observed chapter marks, past papers, and topic-wise practice for CA Intermediate:

Open in Interactive Practice Hub · Full Practice Hub · More in this subject