Based on the data below, what is the amount of the overhead under-/over-absorbed? Budgeted overhead - 5,25,000 Budgeted machine hours- 17,500 Actual…

CA Intermediate · Cost and Management Accounting · MTP · May 2024
Based on the data below, what is the amount of the overhead under-/over-absorbed? Budgeted overhead - 5,25,000 Budgeted machine hours- 17,500 Actual machine hours- 17,040 Actual overheads-5,20,000
(A) A. 5,000 under-absorbed
(B) B. 8,800 under-absorbed
(C) C. 8,800 over-absorbed
(D) D. 5,000 over-absorbed

Suggested Answer and Working Notes:

Correct Answer: Option (B)

B. 8,800 under-absorbed

Topics: Budgets and Budgetary Control, Overheads - Absorption Costing Method