The following extract is taken from the overhead budget of X: Budgeted activity 50% 75% Budgeted overhead (₹) 30,00,000 40,00,000 What would be the…

CA Intermediate · Cost and Management Accounting · MTP · May 2024
The following extract is taken from the overhead budget of X: Budgeted activity 50% 75% Budgeted overhead (₹) 30,00,000 40,00,000 What would be the budgeted overhead for 60% level of activity:
(A) A. 32,00,0000
(B) B. 34,00,000
(C) C. 30,00,000
(D) D. 36,00,000

Suggested Answer and Working Notes:

Correct Answer: Option (B)

B. 34,00,000

Topics: Budgets and Budgetary Control, Overheads - Absorption Costing Method