Standard hours required for doing a work is 100 hours and budgeted hours is 120 hrs. while the same work is actually completed by workers in 110…

CA Intermediate · Cost and Management Accounting · MTP · May 2026
Standard hours required for doing a work is 100 hours and budgeted hours is 120 hrs. while the same work is actually completed by workers in 110 hrs. You are required to calculate the activity ratio:
(A) 109.09%
(B) 83.33%
(C) 90.90%
(D) 110%

Suggested Answer and Working Notes:

Correct Answer: Option (B)

83.33%

Topics: Budgets and Budgetary Control