Standard hours required for doing a work is 100 hours and budgeted hours is 120 hrs. while the same work is actually completed by workers in 110…
CA Intermediate · Cost and Management Accounting · MTP · May 2026
Standard hours required for doing a work is 100 hours and budgeted hours is 120 hrs. while the same work is actually completed by workers in 110 hrs. You are required to calculate the activity ratio:
Suggested Answer and Working Notes:
Correct Answer: Option (B)
83.33%
Topics: Budgets and Budgetary Control
Related Questions in this Topic
- (a) You have been asked to install a costing system in a manufacturing company. What practical difficulties will you exp...
- Apex Mobility Systems Ltd. manufactures smart airport luggage carts used in major international airports. The company op...
- ABC Ltd., a mid-sized manufacturing company, has been facing frequent cost overruns and profit fluctuations over the pas...
- The following figures are extracted from the books of a company: Budgeted overheads ₹ 20,000 (Fixed ₹ 12,000, Variable ...
- A business manufactures a single product and is preparing its production budget for the year ahead. It is estimated that...