A manufacturing unit has budgeted standard hours of 15,000 for May 2025. During the month, the capacity utilisation ratio was 85%, while the efficiency ratio stood at 110%. The factory reported smooth operations with no major downtime. The standard hours allowed for May 2025 was:
(A) 14,025
(B) 13,200
(C) 15,750
(D) 12,900

Suggested Answer and Working Notes:

Correct Answer: Option (A)

14,025