Suppose the units of a product are produced at the rate of 4 units per useful direct labour hour. Direct labour idle time is 10% of hours paid for.…

CA Intermediate · Cost and Management Accounting · RTP · September 2025
Suppose the units of a product are produced at the rate of 4 units per useful direct labour hour. Direct labour idle time is 10% of hours paid for. Sales of 1,000 units are budgeted and finished goods stock is expected to rise by 100 units. The budgeted direct labour hours for the production would be:
(A) 306
(B) 250
(C) 275
(D) 400

Suggested Answer and Working Notes:

Correct Answer: Option (A)

306

Topics: Budgets and Budgetary Control, Employee Cost & Direct Expenses