The Budgeted fixed overhead for the month of August was - 75,00,000 with the units of production estimated at 15,000. However, the actual units…

CA Intermediate · Cost and Management Accounting · MTP · January 2025
The Budgeted fixed overhead for the month of August was - 75,00,000 with the units of production estimated at 15,000. However, the actual units produced is 15,600 with no Fixed overhead cost variance. CALCULATE the actual fixed overhead incurred.
(A) ₹ 75,00,000
(B) 72,11,538
(C) 78,00,000
(D) 79,00,000

Suggested Answer and Working Notes:

Correct Answer: Option (C)

78,00,000

Topics: Budgets and Budgetary Control, Overheads - Absorption Costing Method