(ii) The Plant and Machinery, having a cost price of ₹ 67,50,000, had a written down value of ₹ 52,02,000 as on 1st April, 2025 (iii) The Office…

CA Intermediate · 4 - Cost and Management Accounting · RTP · January 2027
(ii) The Plant and Machinery, having a cost price of ₹ 67,50,000, had a written down value of ₹ 52,02,000 as on 1st April, 2025 (iii) The Office Building, costing ₹ 1,80,00,000, carried a written down value of ₹ 1,62,00,000 as on 1st April, 2025 (iv) Depreciation on Factory Building, Plant and Machinery & Office Building is charged on the written down value method @ 10%, 15% and 10% respectively. (v) Insurance cost of the Factory Building & Plant and Machinery is 2% each of its cost price with no insurance cover for Office Building. Additional information: (i) The value of raw materials held in stock was ₹ 15,30,000 as on 1st April, 2025 and ₹ 8,10,000 as on 31st March, 2026, whereas the value of work-in-progress was ₹ 24,75,000 as on 1st April, 2025 and ₹ 15,75,000 as on 31st March, 2026. (ii) Stock of finished goods as on 1st April, 2025 was 80,000 units having a total cost of ₹ 36,00,000. The entire stock of opening finished goods is sold during the year and the closing stock is 70,000 units. During the period, 4,50,000 units were sold. (iii) The Company wants a profit of 25% on cost of sales. You are required to PREPARE a Cost Statement showing the various elements of cost and the profit earned for the year ended 31st March, 2026.

Suggested Answer and Working Notes:

Cost Statement for the year ended 31st March, 2026 Particulars (₹) (₹) Raw Material Consumed: Opening Stock 15,30,000 Less: Closing Stock (8,10,000) 7,20,000 Direct Wages 1,08,00,000 Direct Expenses Prime Cost 1,15,20,000 Add: Factory Overheads: Depreciation on Factory Building (W.N. 1) 11,25,000 Depreciation on Plant & Machinery (W.N. 2) 7,80,300 Insurance premium for plant & machinery (₹ 67,50,000 × 2%) 1,35,000 Insurance premium for factory building (₹ 1,12,50,000 × 2%) 2,25,000 Salary paid to supervisors 27,80,550 49,05,000 Gross factory cost 1,64,25,000 Add: Opening value of W-I-P 24,75,000 Less: Closing value of W-I-P (15,75,000) Factory Cost 1,73,25,000 Quality control cost: Expenses paid for quality control check activities 19,35,000 19,35,000 Administration cost related with production: Salary paid to Production Control Manager 32,40,000 32,40,000 Less: Realisable value on sale of scrap (2,25,000) Add: Primary packing cost 13,50,000 Cost of Production 2,36,25,000 Add: Opening stock of finished goods (80,000 units) 36,00,000 Less: Closing stock of finished goods (70,000 units) (31,50,000) Cost of Goods Sold 2,40,75,000 Administrative overheads: Depreciation on office building (₹ 1,62,00,000 x 10%) 16,20,000 Salary paid to General Manager 55,80,000 Fee paid to independent directors 22,50,000 94,50,000 Selling overheads (4,50,000 units x ₹ 9) 40,50,000 Cost of Sales 3,75,75,000 Add: Profit (25% on cost of sales) 93,93,750 Sales 4,69,68,750 Working Note: Calculation of value of closing finished goods Number of units produced = Units sold + Closing stock - Opening stock = 4,50,000 + 70,000 - 80,000 = 4,40,000 units Per unit cost = Cost of Production / Number of units produced = ₹ 1,98,00,000 / 4,40,000 units = ₹ 45 per unit Value of Closing stock = ₹ 45 × 70,000 units = ₹ 31,50,000

Topics: Activity Based Costing

ICAI Exam Preparation & Marks Distribution Resources

Explore observed chapter marks, past papers, and topic-wise practice for CA Intermediate: