What would be Prime cost from below information? Direct materials Purchased : ₹75,000 Direct labour : ₹45,000 Direct expenses : ₹15,000…
CA Intermediate · Cost and Management Accounting · MTP · September 2026
What would be Prime cost from below information? Direct materials Purchased : ₹75,000 Direct labour : ₹45,000 Direct expenses : ₹15,000 Manufacturing overheads : ₹22,500 Direct materials consumed : ₹67,500
Suggested Answer and Working Notes:
Correct Answer: Option (B)
(B) ₹1,27,500
Topics: Overheads - Absorption Costing Method, Cost Sheet
Related Questions in this Topic
- NutritionCrunch Pvt. Ltd. is a fast-growing company in the health food industry, specializing in the production of nutri...
- In a factory, the average annual charges for direct wages amounts to ₹ 4,80,000. The following are some of the expenses ...
- Pre-determined factory overhead rate was ₹ 15 per labour hour. Actual labour hour worked 60,000. Actual factory overhead...
- The following figures are extracted from the books of a company: Budgeted overheads ₹ 20,000 (Fixed ₹ 12,000, Variable ...
- Pinky Ltd. Produces product A in batches; management of Pinky Ltd. wants to know the number of batches of product A to b...