A company is preparing a quotation for a customised engineering project. The project requires 40 kg of Material P. The company has 200 kg of…

CA Intermediate · 4 - Cost and Management Accounting · MTP · September 2026
A company is preparing a quotation for a customised engineering project. The project requires 40 kg of Material P. The company has 200 kg of Material P in stock, originally bought at ₹10 per kg. Material P, if processed further at a cost of ₹3 per kg, can be converted into Material Q, which the company currently purchases from the market at ₹9 per kg. What is the relevant cost of using Material P for the new project? What is the relevant cost of using Material P for the new project?

Options:

  1. (A) ₹40
  2. (B) ₹160
  3. (C) ₹240
  4. (D) ₹200

Suggested Answer and Working Notes:

Correct Answer: Option (C)

Correct answer: (C) ₹240.

Topics: Marginal Costing

ICAI Exam Preparation & Marks Distribution Resources

Explore observed chapter marks, past papers, and topic-wise practice for CA Intermediate:

Open in Interactive Practice Hub · Full Practice Hub · More in this subject