Net Present value≥ 0, then

CA Foundation · Quantitative Aptitude · MTP · June 2024
Net Present value≥ 0, then
(A) A. Accept the Proposal
(B) B. Reject the proposal
(C) C. Not Feasible
(D) D. None of the above

Suggested Answer and Working Notes:

Correct Answer: Option (A)

A. Accept the Proposal