Which project would have been recommended by Mr. Harsh? Explain whether his opinion will change, if coefficient of variation is used as a measure of…
CA Final · Integrated Business Solutions (Multidisciplinary Case Study) · MTP · May 2024
Which project would have been recommended by Mr. Harsh? Explain whether his opinion will change, if coefficient of variation is used as a measure of risk.
Suggested Answer and Working Notes:
On the basis of standard deviation project Dehradun Plant be chosen because it is less risky than Project Borsad Plant having higher standard deviation. Decision on the basis of CV: CV of project Dehradun Plant = SD/ENPV = 1,80,00,000/ 2,44,00,000 = 0.738 CV of project Borsad Plant = 2,40,00,000/4,50,00,000 = 0.533 On the basis of Co-efficient of Variation (C.V.) Project Dehradun Plant appears to be riskier and hence, project Borsad Plant should be accepted.
Related Questions in this Topic
- A Ltd., an established player in the hospitality industry, oversees its subsidiary B Ltd., which specializes in the tour...
- A Ltd., an established player in the hospitality industry, oversees its subsidiary B Ltd., which specializes in the tour...
- A Ltd., an established player in the hospitality industry, oversees its subsidiary B Ltd., which specializes in the tour...
- Emergence of Green Entrepreneurship India's remarkable economic progress, marked by its position as the fastest-growin...
- Emergence of Green Entrepreneurship India's remarkable economic progress, marked by its position as the fastest-growin...