A company is considering Projects X and Y with following information: Project Expected NPV (₹) Standard deviation X 1,22,000 90,000 Y 2,25,000…
CA Final · Advanced Financial Management · MTP · January 2026
A company is considering Projects X and Y with following information: Project Expected NPV (₹) Standard deviation X 1,22,000 90,000 Y 2,25,000 1,20,000 (i) Which project will you recommend based on the above data? (ii) Explain whether your opinion will change, if you use coefficient of variation as a measure of risk. (iii) Which measure is more appropriate in this situation and why?
Suggested Answer and Working Notes:
(i) On the basis of standard deviation project X be chosen because it is less risky than Project Y having higher standard deviation. (ii) CVx = SD / ENPV = 90,000 / 1,22,000 = 0.738 CVy = 1,20,000 / 2,25,000 = 0.533 On the basis of Co-efficient of Variation (C.V.) Project X appears to be riskier and hence Y should be accepted. (iii) However, the NPV method in such conflicting situation is best because the NPV method is in compatibility of the objective of wealth maximisation in terms of time value.
Topics: Advanced Capital Budgeting Decisions
Related Questions in this Topic
- ABC Ltd. operates a fleet of cabs. One of its lot of cabs has completed its useful life of 10 years and has been fully d...
- Alpha Green Energy Ltd. (AGEL), a listed company engaged in manufacturing renewable energy equipment, is evaluating the ...
- KLM Ltd., is considering taking up one of the two projects-Project-A and Project-B. Both the projects having same life r...
- Tension Free Solutions (TFS) is a reputed is logistic service providers. All the deliveries are made by drivers of the m...
- D and Co.is a company which installs pipes for supply of oxygen in the hospitals as per their specifications. It is plan...