FSY & Co., Chartered Accountants, completed the statutory audit of HIMMAT Ltd. for the year ended 31st March 2025. The audit partner instructed…
CA Intermediate · Auditing and Ethics · RTP · January 2026
FSY & Co., Chartered Accountants, completed the statutory audit of HIMMAT Ltd. for the year ended 31st March 2025. The audit partner instructed the audit team to finalize and assemble the audit documentation immediately after signing the auditor's report on 15th September 2025. However, audit team took this instruction lightly and forgot to assemble the audit documentation. After six months, audit team started assembling the file and completed its documentation. When audit partner became aware of this, he called a meeting of staff and discussed policies and procedures for timely completion of audit files, changes to audit documentation and period of retention of engagement documentation. Explain various points discussed by audit partner with reference to relevant standard on auditing.
Suggested Answer and Working Notes:
As per SA 230, "Audit Documentation", the auditor shall assemble the audit documentation in an audit file and complete the administrative process of assembling the final audit file on a timely basis after the date of the auditor's report. SQC 1, "Quality Control for Firms that perform Audits and Review of Historical Financial Information, and other Assurance and related services", requires firms to establish policies and procedures for the timely completion of the assembly of audit files. An appropriate time limit within which to complete the assembly of the final audit file is ordinarily not more than 60 days after the date of the auditor's report. The completion of the assembly of the final audit file after the date of the auditor's report is an administrative process that does not involve the performance of new audit procedures or the drawing of new conclusions. Changes may, however, be made to the audit documentation during the final assembly process, if they are administrative in nature. Examples of such changes include: Deleting or discarding superseded documentation.Sorting, collating and cross-referencing working papers.Signing off on completion checklists relating to the file assembly process.Documenting audit evidence that the auditor has obtained, discussed and agreed with the relevant members of the engagement team before the date of the auditor's report. After the assembly of the final audit file has been completed, the auditor shall not delete or discard audit documentation of any nature before the end of its retention period. SQC 1 requires firms to establish policies and procedures for the retention of engagement documentation. The retention period for audit engagements ordinarily is no shorter than seven years from the date of the auditor's report, or, if later, the date of the group auditor's report.
Topics: Audit Documentation
Related Questions in this Topic
- ABC & Co., Chartered Accountants, have completed the audit of PQR Ltd., a large and complex entity, for the financial ye...
- MP Infrastructure Limited for the financial year ended 31st March, 2026. The company had multiple manufacturing units, s...
- M/s TKR & Associates, Chartered Accountants, were conducting the statutory audit of Digital Solutions Ltd., a company op...
- ABC & Co., Chartered Accountants is conducting the statutory audit of a listed company having multiple locations and a l...
- During the audit of a manufacturing company, the engagement team encountered several complex areas requiring careful eva...