M/s BPA & Associates, Chartered Accountants, was appointed as the auditors of Nissan Ltd., a company with PAN-India presence, for the financial…

CA Intermediate · Auditing and Ethics · PYQS · May 2025
M/s BPA & Associates, Chartered Accountants, was appointed as the auditors of Nissan Ltd., a company with PAN-India presence, for the financial year 2023-24. The audit report was issued on August 20, 2024. Following the issuance of audit report, CA P instructed junior team member Mr. Y to assemble the final audit file and prepare the Completion Memorandum. (i) Explain the meaning and significance of a Completion Memorandum. (2 Marks) (ii) Team Member Y completed the assembly of the final audit file in March 2025 and handed it over to CA P. Was team member Y correct in his approach? (2 Marks)

Suggested Answer and Working Notes:

(i) Meaning and Significance of Completion Memorandum: The auditor may consider it helpful to prepare and retain as part of the audit documentation a summary (sometimes known as a completion memorandum) that describes- the significant matters identified during the audit andhow they were addressed. Such a summary may facilitate effective and efficient review and inspection of the audit documentation, particularly for large and complex audits. Further, the preparation of such a summary may assist auditor's consideration of the significant matters. It may also help the auditor to consider whether there is any individual relevant SA objective that the auditor cannot achieve that would prevent the auditor from achieving the overall objectives of the auditor. (ii) Assembly of the Final Audit File: As per SQC 1, "Quality Control for Firms that perform Audits and Review of Historical Financial Information, and other Assurance and related services", the auditor shall assemble the audit documentation in an audit file and complete the administrative process of assembling the final audit file on a timely basis after the date of the auditor's report. An appropriate time limit within which to complete the assembly of the final audit file is ordinarily not more than 60 days after the date of the auditor's report. In the given case, the audit report was issued on August 20, 2024 and CA P instructed team member Mr. Y to assemble the final audit file and to prepare completion memorandum. However, Mr. Y completed the assembly of the final audit file in the month of March 2025, i.e. more than 60 days, is non-compliance of SQC 1. Thus, the approach of team member Y is not correct.

Topics: Audit Documentation

Open in Interactive Practice Hub · Full Practice Hub · Chapter Weightage · More in this subject