A company observes that the consumption of raw materials varies between 300 units and 900 units per week. The lead time ranges from 3 weeks to 7…

CA Intermediate · Cost and Management Accounting · MTP · January 2026
A company observes that the consumption of raw materials varies between 300 units and 900 units per week. The lead time ranges from 3 weeks to 7 weeks, and the reorder quantity is 2000 units. What is the maximum stock level?
(A) 8,100 units
(B) 7,700 units
(C) 6,800 units
(D) 7,400 units

Suggested Answer and Working Notes:

Correct Answer: Option (D)

7,400 units

Topics: Material Cost