A company is working in manufacturing sector and uses labour-force, which consists of skilled, semi-skilled, and unskilled workers. The rate of…
CA Intermediate · Cost and Management Accounting · MTP · May 2025
A company is working in manufacturing sector and uses labour-force, which consists of skilled, semi-skilled, and unskilled workers. The rate of Labour per week for skilled worker is 120, for semi-skilled workers is 80and for unskilled worker is 60. It had planned the labour for a job that would take 60 weeks to be completed, ideally. Ratio of workers employed in skilled, semi-skilled, and unskilled would be 5:3:4. The management consultant who was employed to handle this job died in an accident. Board hired a new consultant to take over this job. This new consultant had a different approach for doing this job. He thought that workers actually required would be in the ratio of 7:3:8. He changed the composition of labour-force and employed the workers in the new ratio. Project was carried out successfully and it turned out that this change in Mix of labour-force saved the company - 76,800 in the job but at the same time company also lost - 1,29,600 due to poor productivity of the labourers. As a result, management consultant was promoted and labour force was fired & was replaced with more experienced labour-force. As the new management consultant was promoted, company found a new one to replace him. This 3 rd management consultant was asked to understand and analyse the previous job done by the 2 nd management consultant. Data in addition to above-given information was provided as follows:- Net extra cost spent, in comparison to planned cost, was - 1,04,000.Total number of weeks worked by all the type of labourers was 23,040 weeks.Skilled and semi-skilled labourers in reality charged 20extra per week, whereas unskilled labourers were negotiated to charge 20less per week, than what they had charged earlier. Let say, you are the 3 rd management consultant, and you have been given with all this information. Work out calculations and answer the following questions (MCQs 6 to 10) based on the information given above.
Suggested Answer and Working Notes:
Correct Answer: Option (A)
1,82,400 (Adverse)
Topics: Standard Costing
Related Questions in this Topic
- ABC Manufacturing Ltd. is a medium-sized manufacturing company engaged in the production of a single industrial componen...
- Standard costs, marginal costs are some of the types of cost which helps the management in decision making. DISCUSS any ...
- Following is the standard cost card of a component: Martials 2 Units at ₹ 15 ₹30 Labour 3 Hours at ₹ 20 ₹60...
- Astra Components Pvt. Ltd. is a Tier-2 supplier to the electrical vehicle (EV) industry. The company manufactures a sing...
- BabyMoon Ltd. uses standard costing system in manufacturing one of its product 'Baby Cap'. The details are as follows: ...