During a certain period, 4,000 labour hours were utilized, and the standard hours for actual production were 5,500 hours. The Variable Overhead…
CA Intermediate · Cost and Management Accounting · PYQS · January 2025
During a certain period, 4,000 labour hours were utilized, and the standard hours for actual production were 5,500 hours. The Variable Overhead Efficiency Variance amounted to 15,000 (Favourable). Calculate the Standard Variable Overhead Rate per hour.
Suggested Answer and Working Notes:
Correct Answer: Option (C)
10 per hour
Topics: Standard Costing, Overheads - Absorption Costing Method
Related Questions in this Topic
- ABC Manufacturing Ltd. is a medium-sized manufacturing company engaged in the production of a single industrial componen...
- Standard costs, marginal costs are some of the types of cost which helps the management in decision making. DISCUSS any ...
- Following is the standard cost card of a component: Martials 2 Units at ₹ 15 ₹30 Labour 3 Hours at ₹ 20 ₹60...
- Astra Components Pvt. Ltd. is a Tier-2 supplier to the electrical vehicle (EV) industry. The company manufactures a sing...
- BabyMoon Ltd. uses standard costing system in manufacturing one of its product 'Baby Cap'. The details are as follows: ...