(i) AP Ltd., a construction contractor, undertakes the construction of commercial complex for Kay Ltd. AP Ltd. submitted separate proposals for each…
CA Intermediate · Advanced Accounting · RTP · May 2025
(i) AP Ltd., a construction contractor, undertakes the construction of commercial complex for Kay Ltd. AP Ltd. submitted separate proposals for each of 3 units of commercial complex. A single agreement is entered into between the two parties. The agreement lays down the value of each of the 3 units, i.e.50 Lakh, 60 Lakh and 75 Lakh respectively. Agreement also lays down the completion time for each unit. Comment, with reference to AS- 7, whether AP Ltd., should treat it as a single contract or three separate contracts. (ii) On 1st December, 2023, GR Construction Co. Ltd. undertook a contract to construct a building for 45 lakhs. On 31st March, 2024, the company found that it had already spent - 32.50 lakhs on the construction. Additional cost of completion is estimated at 15.10 lakhs. What amount should be charged to revenue in the final accounts for the year ended 31st March, 2024 as per provisions of AS-7?
Suggested Answer and Working Notes:
(a) (i) As per AS 7 'Construction Contracts', when a contract covers a number of assets, the construction of each asset should be treated as a separate construction contract when: (a) separate proposals have been submitted for each asset; (b) each asset has been subject to separate negotiation and the contractor and customer have been able to accept or reject that part of the contract relating to each asset; and (c) the costs and revenues of each asset can be identified. Therefore, AP Ltd. is required to treat construction of each unit as a separate construction contract as the above-mentioned conditions of AS 7 are fulfilled in the given case. (ii) Cost of construction incurred till date ₹ in lakhs 32.50 Add: Estimated future cost 15.10 Total estimated cost of construction 47.60 Percentage of completion till date to total estimated cost of construction = (32.50/47.60)×100 = 68.28% Proportion of total contract value recognised as revenue for the year ended 31st March, 2024 per AS 7 (Revised) = Contract price x percentage of completion = 45 lakh x 68.28% = 30.73 lakhs. Total cost of construction ₹ in lakhs 47.60 Less: Total contract price (45.00) Total foreseeable loss to be recognized as expense 2.60 According to AS 7, when it is probable that total contract costs will exceed total contract revenue, the expected loss should be recognized as an expense immediately.
Topics: AS 7
Related Questions in this Topic
- A Company has undertaken a contract to construct Railway Over Bridge (ROB), which is expected to be completed in three y...
- A Limited, an Indian company listed on the National Stock Exchange, is engaged in various businesses. Its tourism busine...
- On 1 st April, 2024, Y Limited purchased an industrial plot of land for 50,00,000 for the purpose of constructing a new...
- A construction contractor has entered into a fixed-price contract of 18,000 lacs to construct a bridge within a three-ye...
- A company took a construction contract for 100 lakhs in January, 2024. It was found that 80% of the contract was complet...