AB Contractors undertakes a fixed price contract of 350 Lakhs. Information related to contract is given as under: Material purchased 125 lakhs…
CA Intermediate · Advanced Accounting · PYQS · January 2025
AB Contractors undertakes a fixed price contract of 350 Lakhs. Information related to contract is given as under: Material purchased 125 lakhs Labour charges 95 lakhs Unused material 22 lakhs Estimated future costs to be incurred to complete the contract 115 Lakhs. Payment received as part payment of contract 50 Lakhs. Machinery used for 4 years for the contract. Original cost of the machine is 210 Lakhs. Expected life of machinery is 20 years. What will be the Profit/Loss on the contract?
Suggested Answer and Working Notes:
Correct Answer: Option (A)
Loss on contract 5 lakhs
Topics: Accounting for Reconstruction of Companies
Related Questions in this Topic
- Following is the Balance Sheet of Ellora Limited as at 31 st March, 2025: Particulars Note Amount (₹) Equit...
- Given below is the Balance Sheet of ABC Ltd. as at March 31, 2026: Particulars Notes ₹ Equity and Liabilitie...
- Following is the Balance Sheet of Tourna Limited as at 31st March, 2025: Particulars Rs. Equity and Liabilitie...
- The business of MA Limited was being carried on continuously at losses. The following are the extracts from the balance ...
- Following is the summarized Balance Sheet of Star Ltd. as on 31st March, 2025. Particulars Amount (₹) Liabilit...