On 31st March 2024, Sri Radhey shyam Enterprise finds that the cost of a partly finished unit on that date is 530. The unit can be finished in…
CA Intermediate · Advanced Accounting · MTP · January 2025
On 31st March 2024, Sri Radhey shyam Enterprise finds that the cost of a partly finished unit on that date is 530. The unit can be finished in 2024-25 by an additional expenditure of 310. The finished unit can be sold for 750subject to payment of 8% brokerage on the selling price. Sri Radhey shyam Enterprise seeks your advice regarding the amount at which the unfinished unit should be valued as at 31st March, 2024 for preparation of final accounts. the partly finished unit cannot be sold in semi-finished form and its NRV is zero without processing it further.
Suggested Answer and Working Notes:
Correct Answer: Option (D)
₹ 440
Topics: AS 2, AS 13
Related Questions in this Topic
- Sun Ltd. has fabricated special equipment (solar power panel) during 2024-2025 as per drawing and design supplied by the...
- In the books of G Ltd., closing inventory as at 31.03.2026 amounts to ₹10,40,000 (on the basis of FIFO method). The com...
- Following is the example of research activities as per AS 26 which is recognised as expense when it is incurred:
- P Ltd. has 60% voting right in Q Ltd. Q Ltd. has 20% voting right in R Ltd. Also, P Ltd. directly enjoys voting right of...
- In the following cases, find the value of closing stock as per AS 2: (i) Sonu is a retailer dealing in toys. During the...