Woollen Garments Limited entered into a contract with a group of women in July, 2023 to supply various woollen clothes for men, women and kids like…

CA Foundation · Business Laws · PYQS · September 2024
Woollen Garments Limited entered into a contract with a group of women in July, 2023 to supply various woollen clothes for men, women and kids like sweaters, monkey caps, mufflers; woollen coats, hand gloves etc. before the commencement of the winter season. The agreement expressly provides that the woollen clothes shall be supplied by the end of October, 2023 before starting of winter season. However, due to the prolonged strike, women group could tender the supplies in March, 2024 when the winter season was almost over. Analysing the situation and answer the following questions in light of the provisions of the Indian Contract Act, 1872: (A) Whether company can reject the total supply by women group? (B) Whether company can accept the total supply on request of women group?

Suggested Answer and Working Notes:

(a) According to section 55 of the Indian Contract Act,1872, when a party to a contract promises to do certain thing at or before the specified time, and fails to do any such thing at or before the specified time, the contract, or so much of it as has not been performed, becomes voidable at the option of the promisee, if the intention of the parties was that time should be of essence of the contract. Effect of acceptance of performance at time other than agreed upon - If, in case of a contract voidable on account of the promisor’s failure to perform his promise at the time agreed, the promisee accepts performance of such promise at any time other than agreed, the promisee cannot claim compensation for any loss occasioned by the non-performance of the promise at the time agreed, unless, at the time of acceptance, he gives notice to the promisor of his intention to do so. In the instant case, (A) Woollen Garments Limited is legally entitled to reject the goods due to the failure to meet the delivery deadline, as time was a crucial term of the contract. (B) The company cannot accept the total supply on the request of woman group but only when the company i.e. buyer elects to do so. In that case, the company cannot claim compensation for any loss occasioned by the non-performance of the promise (i.e. delay in supply).

Topics: The Indian Contract Act, 1872, The Indian Contract Act, 1872, The Indian Contract Act, 1872

Open in Interactive Practice Hub · Full Practice Hub · Chapter Weightage · More in this subject

Related Questions in this Topic